Teamwork triumphs in Heysham bridge demolition
It was a ‘sprint to the
line’ as Controlled Group and fellow contractors battled to complete the
demolition of Berth No.1 before the new link span bridge arrived at Heysham
Port, near Lancaster, after its five day journey by sea from Rotterdam. With
the divers still in the water burning out the last of the foundation
reinforcing as the new bridge appeared on the horizon, it was a dramatic scene.
Since the start of the
demolition Controlled Group had removed the winch house, portal cross beam and
supporting column and blasted the buttress and foundation above and below the
waterline. This was a project that proved to be a true test of man’s struggle
with the extremes of nature, culminating in the nail-biting climax that now
faced them.

The old link span bridge
with its concrete portal and winch house is one of three berths for the ferries
and freightliners travelling across the Irish Sea
between Heysham and the Isle of Man and Belfast. The other two berths remained
operational during the demolition. The new £5.2m link span bridge is a two-lane
carriageway, twice as wide as the old bridge, which will halve the ferry
turn-around times for Berth No.1.
Planning for the 18-day
project began back in October 2006. Surveys and inspections were carried out
and the weight of each element accurately calculated as most of the structure
was to be lifted out by floating crane. The lower part of the reinforced
concrete buttress was to be blasted.
With only minutes to spare,
the Mersey Mammoth and long-reach machine finished removing the last of the
demolition debris before the new link-span bridge was floated into the harbour. The three sea-going tugs manoeuvred
the bridge so it could be tirfored the last few feet
onto its new bearings and bank-seat, prepared by Nuttall
John Martin.
“Possession of the old
Berth No.1 was taken on the 28th December 2006 and in only three days all the
heavy lifting had been completed. This was a tribute to the previous month of
meticulous planning” says Rob Clarke, Controlled Group’s in-house Structural
Engineer.

Phase 1 – The Heavy
Lifting
The Winch House
The first task was to
remove the winch house, which was used to automatically raise and lower the old
bridge with the changing tide. The cables and bolts between the winch house and
bridge had to be cut and burned through. Two lifting beams were specially
fabricated to lift the winch house, complete with 50 tonnes
of winding gear. It was removed using the Mersey Mammoth – a floating
crane with the capacity to lift up to 300 tonnes.
“The Mammoth with its eight-man crew is a marvellously
versatile tool,” enthuses Rob.
The Portal Cross-beam
The Mersey Mammoth was
also used to remove the portal cross-beam between the two columns. An old
locomotive lifting beam was dusted down to suspend the 100 tonne capacity wire
ropes used to lift the 160 tonne reinforced concrete cross-beam. Early partial
diamond wire saw cuts were made through the beam prior to the full possession.
Therefore once the final cuts through the 2.4m sq, 10m long reinforced concrete
beam had been made, it was raised using wire rope slings. Each 100 tonne
capacity sling was 4 inches in diameter. The difficulty here was safely
climbing onto the beam to pull the wire ropes down and up round the other side
to hook them onto the lifting beam. A 50 tonne mobile crane had to be used to
hold the ends of the slings while they were secured.
The supporting column
Nationwide Diamond
Drilling cored a 7-inch diameter hole through the middle of the remaining 2.4m
sq 7m tall column. Then a 6 inch mild steel shaft was inserted for lifting.
After a four hour long final saw-cut was made, the slings were attached to each
end of the shaft, and the 110 tonne monolith was hoisted away by the Mammoth.
The link-span bridge
With the high level
structure gone, there was now space to lift out the 150 tonne steel trussed
bridge. However, the team had to move quickly. Strong westerly winds were being
forecast for the next two weeks. In addition, the far end of the bridge was
resting on the seabed and the chains and shackles had to be secured around the
bottom boom before the bridge became submerged by the advancing tide.
Access was difficult, but
using a 50ton mobile crane and man-basket, shackles carried in two safety boats
and the Mammoth holding the slings, everything was connected for the lift. With
great skill the Mammoth kept the bridge steady in three directions, made a
clean lift and transported the old steel structure to the south quay for
processing, all just before the wind became too strong.
Phase 2 – The
Explosives
With the heavy lifting
completed, now it was time for the explosives. This was going to be the fastest
and safest way to destroy the massive reinforced concrete buttress and
foundation that now stood isolated, 10m from the quayside. Charging holes were
drilled three metres deep into the top of the buttress. Heavy purpose made blast-mats were craned into position over the
buttress. The blast-mats prevent any fly, fragments of concrete and steel, from
being ejected by the blast.

After evacuating the
150-metre exclusion zone area the first section was detonated. The concrete
shattered and was held loosely in place by the reinforcement cage. A 30 ton
long-reach machine, equipped with hammer and
bucket, standing on a
floating pontoon working platform, then cleaned away the shattered concrete
debris. After the reinforcement was burnt off, the process was repeated and the
next level of charging-holes were drilled. This procedure
was repeated four times until cut-off level was reached, 3m below low-tide
level.
“In practice this was not
at all easy,” says Controlled Group’s Explosives Director, Mick Williams.
“Burning the rebar had to be done from a man-basket suspended from a crane on
the quay side. And this was during the period when the high winds were at their
worst.
“Overnight, the pontoon
which was carrying the 30 tonne long-reach machine became damaged whilst moored
against the north quay. Lorries were being blown over on the M6 by the westerly
winds and the conditions in the harbour were
horrendous” says Mick. “The pontoon’s steel box panels began to leak and it
slowly sank with the long-reach machine chained securely to it. We couldn’t
believe our bad luck. The Mersey Mammoth had to return from its home in
Liverpool to recover the pontoon and the long-reach!”
Noisy neighbours
Heysham Nuclear Power
Station is a mere 500m from the blast site and not surprisingly power station
officials were a little apprehensive about the potential power of the blasts
and vibration coming from the Port area.
“We provided them with
predictions of expected vibration levels, and carried out a test blast before
beginning the operation,” says Mick. “As expected the vibration levels were
negligible,”
Dealing with the
unexpected
Meanwhile, unusually low
river levels in Holland delayed the launch and departure of the new link span
bridge. As it turned out, this
allowed the demolition team extra time to deal with another unexpected problem.
“We discovered a lot of
steel temporary works cast into the foundations of the bridge,” explains Rob.
“Old railway lines had been cast into the concrete base and were supported on a
steel frame during the pour. The final blast using 70kg of explosives was not
enough to rip this out. We had to use a team of divers to burn away the
remaining buried steelwork with thermic lances.”
The divers’ work was synchronised with the long-reach machine hammering and
clearing debris, a job that continued round the clock for 48 hours, working
around the tides and in between ferry manoeuvres.
Just in time!
The new bridge was now on
its way from Rotterdam. But
burning steel under water in the murky Irish Sea is no easy task. Visibility
was so poor that the divers couldn’t tell which piece of steel they were
cutting and how many times they had cut it. Somehow, however, the divers and
machine driver managed to clear away all the concrete and reinforcement debris
in the channel to make space for the new bridge with just three minutes to
spare!
“As you can imagine we
were so relieved,” says Rob. “This project had consisted of a series of highs
and lows and the constant pressure of the tight timescale, so it was great to
be able to go out on a high.”
Rob concludes that the
demolition of the Heysham link bridge was one of the most unusual challenges of
his career and a large part of its ultimate success was due to the high
standards of cooperation between all those involved.
“It was a great example of teamwork in practice and I would
certainly work with any of the contractors involved again,” he says. “The Port
staff, the Mersey Mammoth crew, the Diamond Drillers, crane drivers, long-reach
drivers and Nuttall John Martin all worked together
really well. Despite having to deal with the tides, the ferry movements and
some of the severest weather conditions, remarkably, we pulled it off.